- P1 issues. If a request was received from production usage or escalation from Capacity Planning Group. Each P1 issue should be reviewed by PO, Dev Lead, and SM.
...
- Tickets from the current sprint:
...
- Unfinished issues
- Ticket at In Code Review state with unresolved
...
- comments.
- Ticket with comments after testing that should be done in the scope of a particular ticket.
...
- Issues that block other tasks in the current sprint.
...
- P2 issues that
...
- have been added to the current sprint without unresolved dependency.
...
- P3/P4 issues that
...
- have been added to the current sprint without unresolved dependency.
...
- Tasks from backlog without unresolved dependency
...
- .
...
- If the task is picked up
...
- into the current sprint see priorities at p#2.