Risk probability | Risk impact | |||||
Probability level | Description | Value | Impact value | Impact description | Value | |
---|---|---|---|---|---|---|
Very low | In past projects experience you have never seen this happen, but it probably could | 0.05 | Very Low | Small monetary loss or a few days of delay | 1 | |
Low | It has happened on occasion | 0.25 | Low | Manageable monetary loss or a few weeks of delay | 2 | |
Moderate | Sometimes it happens and sometimes not | 0.5 | Moderate | Heavy monetary loss or significant delay that doesn't endanger project success in general | 3 | |
High | Most of the time this event happens | 0.75 | High | A loss or a delay that can endanger overall project success | 4 | |
Very high | It has happened on almost every project and you think it always will but there is a chance of escape | 0.95 | Very high | Project failure and possible additional losses | 5 |
Risk
...
Exposure
Risk exposure value is calculated by the given formula:
...
Probability | Risk exposure | Color | Risk priority | |||||||
---|---|---|---|---|---|---|---|---|---|---|
0.05 | 0.25 | 0.5 | 0.75 | 0.95 | 0 - 0.75 | Green | Low risk | |||
I M P A C T | 1 | 0.05 | 0.25 | 0.5 | 0.75 | 0.95 | 0.95 – 2.25 | Amber | Moderate risk | |
2 | 0.1 | 0.0.5 | 1 | 1.5 | 1.9 | 2.5 – 4.75 | Red | Critical risk | ||
3 | 0.15 | 0.75 | 1.5 | 2.25 | 2.85 | Prioritization of risks must be done based on Risk Exposure value as follows:
| ||||
4 | 0.2 | 1 | 2 | 3 | 3.8 | |||||
5 | 0.25 | 1.25 | 2.5 | 3.75 | 4.75 |
Risk category | Risk source | Risk Description/Summary | Risk Probability | Risk Impact | Risk Exposure | Risk Exposure | Risk status (open/treated) | Risk Treatment Strategy (avoidance/ reduction) | Last Update date | Mitigation Plan (Treatment strategy description) | Assignee | Date of Risk Occurrence | Issue Status | Contingency Plan | Contingency Plan Assignee |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
...