Batch Importer (Bib/Acq) (UXPROD-47)

[UXPROD-3726] NFR: UI end-to-end tests tech debt for Folijet (Orchid R1 2023) Created: 27/Jun/22  Updated: 22/Feb/23  Resolved: 22/Feb/23

Status: Closed
Project: UX Product
Components: None
Affects versions: None
Fix versions: Orchid (R1 2023)
Parent: Batch Importer (Bib/Acq)

Type: New Feature Priority: P2
Reporter: Ann-Marie Breaux (Inactive) Assignee: Ann-Marie Breaux (Inactive)
Resolution: Done Votes: 0
Labels: AQA, data-import, epam-folijet, ui-e-to-e-testing
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original estimate: Not Specified

Issue links:
Continues
continues UXPROD-3694 NFR: UI end-to-end tests for Folijet ... Closed
is continued by UXPROD-3839 NFR: UI end-to-end tests tech debt fo... Closed
Defines
defines UXPROD-47 Batch Importer (Bib/Acq) Analysis Complete
is defined by FAT-1677 Implement e-2-e automation of test ca... Closed
is defined by FAT-2743 Implement e-2-e automation of test ca... Closed
is defined by FAT-2778 Implement e-2-e automation of test ca... Closed
is defined by FAT-3570 Implement e-2-e automation of test ca... Closed
is defined by FAT-3571 Implement e-2-e automation of test ca... Closed
is defined by FAT-3590 Implement e-2-e automation of test ca... Closed
is defined by FAT-3597 Implement e-2-e automation of test ca... Closed
is defined by FAT-2738 Implement e-2-e automation of test ca... Closed
is defined by FAT-2760 Implement e-2-e automation of test ca... Closed
is defined by FAT-4394 Folijet E2E automated tests stabiliza... Closed
is defined by FAT-3583 E2E Autotests stabilization Closed
is defined by FAT-4051 Folijet E2E automated tests stabiliza... Closed
is defined by FAT-4144 Folijet E2E automated tests stabiliza... Closed
Relates
relates to FAT-1188 TECH DEBT - Critical Path - UI E2E Au... In Progress
relates to FAT-552 TECH DEBT - Implement UI e-2-e automa... In Progress
relates to UXPROD-3544 NFR: UI end-to-end tests for Data Imp... In Progress
Release: Orchid (R1 2023)
Epic Link: Batch Importer (Bib/Acq)
Front End Estimate: XXL < 30 days
Front End Estimator: Oleksandr Bashtynskyi
Front-End Confidence factor: 90%
Back End Estimate: Out of scope
Development Team: Folijet
PO Rank: 94
Rank: Cornell (Full Sum 2021): R5

 Description   

Ivan Kryzhanovskyi to confirm if there's a particular amount of capacity to be used for this

=======================================================

Ivan Kryzhanovskyi to confirm if there's a particular amount of capacity to be used for this

=======================================================

In scope:

  • Any remaining Data Import Critical Path Tests (Jira P2s) not finished on the previous feature UXPROD-3694 Closed
  • Data Import Critical Path Tests (Jira P3s)
  • If any Data Import Critical Path Tests remain at the end of Orchid, move to a new Poppy feature
  • After Data Import Smoke and Critical Path tests are finished, check for other teams' remaining Smoke and Critical Path tests before moving on to further Folijet E2E tests

Out of scope:

  • Individual unit tests (covered by RTL/Jest work)
  • Performance/stability tests for large files (covered by the Stability feature)
  • Smoke and Critical Path tests for new functionality (should be linked to the feature for the functionality, in the release that the feature is completed in)

Within the tests:

  • Will need to configure the environment
  • Will need appropriate MARC/EDIFACT files (1 record in the file when possible)
  • Will need the appropriate profiles
  • Test covers the workflow from profile creation through finishing the UI log
  • Reset environment after tests

After the tests are written

  • Confirm that they are running and passing on a regular basis
  • Fix any problems identified during the automated runs
  • Retire the manual TestRail case(s) that the automated test replaces
    • See PO if any questions
    • See description here for updating TestRail
  • If possible, add recording of the automated test to the Jira, to show it working


 Comments   
Comment by Ann-Marie Breaux (Inactive) [ 13/Oct/22 ]

Hi Tetiana Paranich and Oleksandr Bashtynskyi I moved the P2 E2Es from the Nolana Folijet feature to this Orchid feature, and the P3s from this Orchid feature to the Poppy feature. That leaves some P1s on the Nolana feature. If any are open when we decide to close the Nolana feature, we'll move them to Orchid. And if you run out of tests on the Nolana feature, pull from this one. Thank you!

Comment by Tetiana Paranich [ 27/Jan/23 ]

Hi Ann-Marie Breaux and Oleksandr Bashtynskyi, I moved tickets were not automated in Orchid release to Poppy release.