95
Estimation Notes and Assumptions
Based on Lotus actual effort:
BE - 34 days
FE - 20 days
Front End Estimate
XXL < 30 days
Front-End Confidence factor
Medium
Back End Estimate
XXXL: 30-45 days
TestRail: Cases
Open TestRail: Cases
TestRail: Runs
Open TestRail: Runs
Created January 14, 2022 at 1:01 PM
Updated September 21, 2022 at 5:49 AM
Resolved August 17, 2022 at 3:32 PM
TestRail: Cases
TestRail: Runs
Overview: For every release the development team will need to release all relevant modules.
Acceptance criteria:
All modules have been released
Any Hotfix releases required for previous release versions are created if backporting of the fixes is required.
All recommended RMB version updates are complete for back-end modules
All recommended Stripes version updates are complete for front-end modules
All recommended migration scripts verification activities are done